Aqua to replace pipe on several blocks on the west side of Conshohocken

Aqua has announced that it will begin replacing 5,200 feet of pipe on the west side of Conshohocken starting August 8th. Being replaced is a 6-inch cast iron pipe with 8-inch ductile iron water main. The streets and blocks involved are as follows:

  • Maple Street from West 1st Avenue to West 3rd Avenue
  • Forrest Street from West 1st Avenue to West 3rd Avenue
  • West 3rd Avenue from Fayette Street to the dead end of West 3rd Avenue
  • West 4th Avenue from Fayette Street to the dead end of West 4th Avenue

The work to replace the pipe is scheduled to take place on weekdays between 7:00 a.m. and 4:00 p.m., however, there may be a need to work on Saturdays. Residents will have access to their properties, but at times will need to enter from a different direction due to changing work zones. Emergency services, mail, and trash collection will be provided access.

The work is expected to last into December.