Developer O’Neill claims data center “deemed approved” due to Plymouth Township not meeting hearing requirements

During the November 19th zoning hearing in Plymouth Township, Developer Brian O’Neill submitted a letter (view) into evidence that had been distributed to the township and party attorneys earlier in the day.

O’Neill is seeking a special exception to allow a data center at the site of a former steel plant at 900 Conshohocken Road in Conshohocken (Plymouth Township). The property falls within the heavy industrial zoning district.

The letter argues that O’Neill’s proposed data center is deemed approved as of June 28, 2026, because the township did not hold a hearing as required by the Pennsylvania Municipalities Planning Code and did not meet other timeline requirements once the application was submitted.

At this point, the letter does not legally trigger any process. The deemed approval process will not legally begin until a public notice is advertised (which hasn’t been done). If the notice is advertised, the parties with standing have 30 days from the date of the advertisement to appeal to the Montgomery County Court of Common Pleas.

First, let’s review the state-mandated timeline. Once a municipality receives a zoning application, the first hearing must be held within 60 days. If the hearing can’t be completed at one meeting and is continued, any subsequent hearings must be held within 45 days. The applicant is allotted up to 100 days from the first hearing to complete presenting its evidence. The zoning board must render a decision within 45 days of the final hearing and deliver it within one day of making the decision. The timeline can be relaxed if agreed to by the applicant.

In the letter distributed on November 19th, it is stated:

The Board received the Application on April 28, 2026. Section 908(1.2) of the MPC [Pennsylvania Municipalities Planning Code] required the Board to commence the first hearing within 60 days of that date, that is, by June 27, 2026. The Board convened on June 25, 2026, but it did not commence a hearing on the Application that evening. The Board’s Solicitor stated at the outset that “tonight’s hearing will be dedicated solely to establishing the parties in this case,” that “testimony will commence at the next hearing,” and that party status was “the only thing we are going to deal with tonight,” and at the close that “we will not be taking any evidence or testimony tonight on the application” (June 25, 2026 Tr. 8:11–16; 10:12–14; 39:15–18).

No Applicant witness was sworn, no Applicant testimony was taken, and the Applicant was afforded no opportunity to present evidence or argument on the Application. The Board then continued the matter on its own motion.

Respectfully, a session at which the applicant is afforded no opportunity to present evidence and argument is not a hearing within the meaning of Section 908(1.2). No hearing having been commenced within 60 days of receipt of the Application, Section 908(9) of the MPC provides that “the decision shall be deemed to have been rendered in favor of the applicant.” The Application was therefore deemed approved as submitted on June 28, 2026.

The letter further claims that if the hearing process was initiated within the mandated timeframe, the applicant was not able to conclude within the 100 days afforded to present his case. The letter points out that the applicant (O’Neill) never agreed to modify the timeline.

It then requests that the board issue the proper notice of approval for the data center. If the board doesn’t take that step, there is then an opportunity for the applicant to advertise it on their own. As of November 23rd, no public notice has been advertised by the township or the developer.

This is a potential third path towards approval. Two different zoning processes are underway. The first involves seeking a special exception to allow the data center. The second is a validity challenge, which claims that the township’s zoning code does not provide for a fair process for approval.

Plymouth Township has not added the letter to its website page dedicated to providing information about this proposed data center. It has also not added the proposed ordinance (view), which won’t impact O’Neill’s current application.

More to come.